• Project Duration: April 2014 - February 2016 (phase 1)
  • Value: ZAR 200 million / USD 14.3 million
  • Brief: Full Infrastructure / Continuous Power
  • Alternator : Site voltage 690V : 33kV

Engineering, procurement and construction of a power plant, complete with bulk diesel (1500kl) and oil (46kl) tanks, manifolds, filtration, and truck offloading bay. The plant is designed for 16 generators rated 1500kW/1875kVA continuous power each, feeding into 4 4MVA step-up transformers into the 33kV overhead bus through open air switchgear. Phase 1 (4 generators and infrastructure) is complete.