(World’s 2nd Largest Uranium Mine, Namibia)

  • Project Duration: October 2014 - June 2016
  • Value: ZAR 70 million / USD 5 million
  • Brief: Full Infrastructure /Cogeneration / Substation control/ Back Up Power
  • Alternator : Site voltage 400V : 33kV

Engineering, procurement and construction of a standby power plant, complete with diesel (46kl) and oil (23kl) tanks, manifolds, pumps and filtration units. The project is based on 7 2MVA prime power generators in combination with 4 4MVA step-up transformers and associated containerised switchgear. Control is extended to the Main Consumer Substation with fully automated synchronisation for seamless transfer and cogeneration with Nampower.

Swakop Uranium – Husab Project